Brisbane 2032 Games build set to squeeze housing supply, report warns
A report warns the Olympic construction boom could worsen Queensland's worker shortage and push up costs for new Brisbane homes and apartments.
A new report warns that Queensland's housing crisis could deepen as construction for the 2032 Brisbane Olympics ramps up. It says worsening affordability and the displacement of low-income households could become the legacy of the Games unless urgent action is taken.
The pressure is already visible on building sites. A manager at Brisbane builder Axiom Construction told Reuters in August that his last three or four concrete pours had been done under head torches and lamps, at night, because he could not find enough workers to do the job in daylight. He acknowledged that poor visibility creates quality problems.
The biggest demand on labour has not yet arrived. The main construction contract for the 63,000-seat Olympic stadium at Victoria Park is expected to be signed in the new year, with the major build starting later in 2027.
The Olympic timeline
This year, the Games delivery authority took possession of Victoria Park on 1 June and fenced off parts of it. In July, Queensland company BMD won the early works contract, covering earthworks, drainage, retaining walls and a logistics area. On 30 September, a joint venture including John Holland became the only remaining bidder for the main stadium contract.
The final price has not been confirmed, but the stadium has been widely reported at about $3.6 billion. It forms part of a $7.1 billion Games venues program funded by the federal and Queensland governments. Colliers puts the full Olympic venue and village pipeline across south-east Queensland at about $11.2 billion through to 2032. Hospitals, highways, energy projects and data centres are competing for the same workforce.
Supporters see opportunity. The authority's chief executive has described the early works as a milestone that creates Queensland jobs, and Colliers' Queensland head says the program offers a rare opportunity for investors, developers and businesses. Community group Save Victoria Park argues the city is giving up one of its few inner-city green spaces.
A growing worker shortage
Figures from Construction Skills Queensland, cited by Colliers, expect the state's construction pipeline to average $69 billion a year and peak at $75 billion in 2027-28. Meeting that would require the industry to grow from about 126,600 workers in 2025-26 to about 148,300 in 2027-28, an increase of more than 21,000 in two years.
A quantity surveying firm forecasts a rolling construction labour shortage in Queensland of 27,200 workers in 2026-27, 43,400 in 2027-28 and 46,000 in 2028-29. The Housing Industry Association says Australia's residential building industry is already about 83,000 skilled workers short nationally, and that Queensland is feeling it strongly.
Home owners are noticing. A comparison by hot water marketplace Pump Swap and platform IBU News found the median wait for a first quote on a heat pump hot water job was about three hours in Victoria but 2.4 days in Queensland. Queensland owners were also about twice as likely to get no installer at all. Pump Swap's founder said that when large infrastructure programs absorb licensed electricians and plumbers, residential work is squeezed.
The HIA's Queensland executive director, Mike Roberts, said the shortage lets tradespeople effectively name their price and leaves builders no option but to pay it. That cost ends up in the price of new homes.
Rising costs and slower builds
The Axiom manager told Reuters that concrete prices have risen nearly 150 per cent in six years, plasterboard is up 46 per cent and pine frames are up about 35 per cent. Master Builders Australia says a typical apartment project now takes 33 months to finish, compared with 21 months a decade ago, while a house takes 11.5 months instead of 8.6.
Longer builds mean more interest costs and risk for builders. Charter Keck Cramer estimates the cost of delivering a comparable middle-ring Brisbane apartment rose from about $345,000 to almost $710,000 per apartment between 2020 and 2025. Separate research for the Property Council puts the full cost of delivering a new Brisbane apartment, including land, fees and finance, at about $1.7 million.
Those figures help explain why Brisbane's apartment pipeline is stalling. If a finished apartment can sell for well below the cost of building it, the project does not start.
Video: Property Roofs.
Key questions
- When will the Brisbane Olympic stadium main contract be signed?
- According to the source, the main construction contract for the 63,000-seat stadium at Victoria Park is expected to be signed in the new year, with the major build starting later in 2027.
- How big is the construction worker shortage in Queensland?
- A quantity surveying firm forecasts a rolling shortage of 27,200 workers in 2026-27, 43,400 in 2027-28 and 46,000 in 2028-29. The Housing Industry Association says residential building is already about 83,000 skilled workers short nationally.
- Why are fewer Brisbane apartments being built?
- Building costs have climbed sharply. One estimate puts the full cost of a new Brisbane apartment, including land, fees and finance, at about $1.7 million. If apartments sell for well below that, projects do not start.